The set we settled on
- Tahoma 3c v2 C1 stucco — from 4.23.2026 CAD
- Tahoma 3c v2 T1 stucco — from 8.7.2026 CAD
- Tahoma 2c v2 T1 stucco — from 8.7.2026 CAD
- Shasta v3 T1 2c stucco — from 8.3.2026 CAD. Note: 2c = T1, 3c = T2. No SE WA lots use the 2c version.
- Shasta v3 T2 3c stucco — from 8.11.2026 CAD. We are also currently building v2 T1, v2 T2 and v3 T1.
- Shasta v3 C1 3c stucco — from 7.6.2026 CAD
Linework checked across the whole set before building — the latest shown in CAD are the ones rendered.
Upcoming model timeline
Out of a chat with Matt G about getting upcoming models rendered early, inside and out, before we hit another logjam. This turned into an email to Mike Dacy.
- Alpine — complete
- Baker — imminent
- Jefferson — imminent
- Helena, Buckner, Ascent — 8.31
- Paulina — 9.02
Matt G let me know the CAD output of Higharc has issues, which I have also seen personally — that will make building from Higharc somewhat more labor-intensive, not less.
Also discussed
- Structural alternates — Shelby will chat with Jessica about whether we want more storytelling for the plan alternates. Still open at 9.02
- Virtual staging — Shelby should have time for style guidelines on Friday. Still open at 9.02
- Overland video — storyline brainstorming with Torri Thu 8.06 at 11am. Went great; her proposal was OK’d by Todd on 8.12. Still need the list of models safe to show; emailed Todd, Nicole, Torri and Shelby. Still open at 9.02